Completion of Track Layout Modification at Pyeongtaek–Jije Station

관리자 2026.01.13

Suwon-bound KTX Project

Phase 1 and Phase 2-1 track layout modification works at Pyeongtaek–Jije Station under the Suwon-bound KTX Direct Connection Project have been successfully completed.

 

Project Overview

  • Project: Suwon-bound KTX Direct Connection Project – High-Speed Railway Train Control System Procurement and Installation (R2024062)

  • Period: August 16, 2024 – March 31, 2027

  • Responsible Unit: Rail Delivery Center & Signal Development Team, Railroad Transportation Business Division

 

Track Layout Modification (Phase 1 & Phase 2-1)

  • Period: December 22, 2025 – January 12, 2026

  • Locations: Dongtan Station, Pyeongtaek–Jije Station, and SRT Suseo Station (Dongtan LCP)

  • Participants: ESTraffic, LS ELECTRIC, KR, KORAIL, Signal Supervisors, and Contractors

  • Key Achievements:

Completion of KR & KORAIL joint tests, including CTC testing
Software cutover of SSI 113, FEPOL, and LCP systems
Cutover of TFM monitoring and electrical technical support systems
    • Phase 1: Commissioning of turnout No. 1544 for high-speed operation

    • Phase 2-1: Decommissioning and partial removal of turnout No. 1521

     